Getting a new electricity meter in Pakistan has become much easier in 2026 thanks to digital services and simplified procedures. Whether you are building a new home or shifting to a new property, you can now apply for a new connection online or by visiting your nearest electricity distribution company office. Companies like LESCO, FESCO, IESCO, and MEPCO provide structured systems where applicants can track their application status and complete the process without unnecessary delays.
Electricity Meter Details Table (2026)
| Meter Type | Phase Type | Load Capacity | Best For | Estimated Cost (PKR) |
|---|---|---|---|---|
| Single Phase | 1-Phase | Up to 5 kW | Small homes | 8,000 – 12,000 |
| Three Phase | 3-Phase | Above 5 kW | Large homes/business | 15,000 – 25,000 |
| Industrial Meter | 3-Phase | High Load | Factories | 50,000+ |
Step-by-Step Process to Apply for New Electricity Meter
Applying for a new electricity connection in Pakistan involves a few simple steps:
- Visit the official website of your electricity provider (e.g., LESCO, MEPCO).
- Open the “New Connection” or ENC (Electricity New Connection) section.
- Fill out the online application form with accurate details.
- Upload required documents like CNIC, property ownership proof, and wiring test report.
- Submit the application and note your reference number.
- Wait for demand notice issuance and pay the required fee.
- After verification, your meter will be installed.
Required Documents for New Meter
To avoid delays, make sure you have the following documents ready:
- Copy of CNIC (Computerized National Identity Card)
- Proof of property ownership or rent agreement
- Neighbor’s electricity bill copy (for reference)
- Wiring contractor’s test report
- Passport-size photographs
Types of Electricity Connections Available
Electricity distribution companies in Pakistan offer different types of connections based on usage:
- Domestic Connection – For residential homes
- Commercial Connection – For shops and offices
- Industrial Connection – For factories and heavy machinery
- Agricultural Connection – For tube wells and farming
Each connection type has different tariffs and requirements.
Online vs Offline Application – Which is Better?
In 2026, the online method is the most recommended way to apply:
- Online Application: Fast, transparent, and trackable
- Offline Application: Requires visiting office and manual processing
Online systems reduce corruption chances and speed up approval time.
Processing Time & Installation Duration
The time required for meter installation depends on the connection type:
- Single Phase: 15–30 days
- Three Phase: 30–45 days
- Industrial: 45–90 days
Delays may occur due to verification issues or incomplete documents.
Eligibility Criteria for New Electricity Meter
To apply for a new electricity meter in Pakistan, you must:
- Be a Pakistani citizen with a valid CNIC
- Own or legally rent the property
- Provide complete and verified documents
- Ensure internal wiring is completed and tested
- Have no outstanding dues on the property
Conclusion
Applying for a new electricity meter in Pakistan in 2026 is now more convenient and transparent than ever. With the introduction of online portals, applicants can submit forms, upload documents, and track progress without visiting offices repeatedly. By preparing the required documents and following the correct process, you can get your electricity connection installed without hassle.
Frequently Asked Questions (FAQs)
1. How can I apply for a new electricity meter online in Pakistan?
You can apply through your electricity company’s official ENC (Electricity New Connection) portal by filling out the application form and uploading required documents.
2. What is the cost of a new electricity meter in 2026?
The cost depends on the meter type. Single-phase meters cost around PKR 8,000–12,000, while three-phase meters can cost up to PKR 25,000 or more.
3. How long does it take to install a new meter?
It usually takes 15 to 45 days depending on the connection type and verification process.
4. Can tenants apply for a new electricity connection?
Yes, tenants can apply with a valid rent agreement and property owner’s permission.
5. What happens after submitting the application?
You will receive a demand notice. After payment and verification, the meter installation process begins.